Welcome to the Datanyx Community!
Get Help, Learn Best Practices, Network With Other Datanyx Users
Notifications
Clear all
Topic starter
22/12/2022 12:24 pm
Step 1: Once data has been imported, click on data preparation. (Refer to the image below).
Step 2: Drag and drop the binning node onto the main screen. Connect the two nodes. (Refer to the image below).
Step 3: Once a successful connection is made between ‘data import and binning’, click on the select button. Binning pop-up appears with the columns present in the data. Click on 'Apply'. (Refer to the image below).
Step 4: Columns can be binned when the user enters value of specific data range.
Step 5: Upon entering the values, click on the run button or the binning node twice and click on the icon in the bottom line. (Refer to the image below).
Step 6: The ‘Binned’ data is reflected in the form of a table. (Refer to the image below).
Note: The user can run the workflow for individual nodes as well.